Tasks, milestones, dependencies and baselines
Break down delivery and retain a plan snapshot.
Before you begin
- Accessible project and edit/planning permission.
Step by step
Add tasks and subtasks with title, estimate and assignee.
Define milestones and finish-to-start dependencies; correct links that create a cycle.
Capture a baseline before changing the plan.
Update statuses, dates and estimates and compare current plan, baseline, actual time and remaining work.
The result to check
Hierarchy and constraints persist and the plan remains comparable over time.
Limits and considerations
- Baselines are immutable.
- Predicted dates depend on estimates and availability, not a delivery guarantee.
Continue with related guides
Projects and sprintsProjects and ticket continuity
Organise a substantial request while preserving its origin and conversation.
↗PlanningGlobal planning and forecastsRead tickets, projects and tasks without counting containers twice.
↗PlanningMy work and team GanttInspect assigned work and personal availability.
↗THE NEXT STEP
Keep following the thread.
Explore the tools or compare plans for your team.